Maintenance Of Spiral Duct Machine
Mar 06, 2023
1. There should be an independent workplace for air duct prefabrication, the working site should be flat and tidy, and the processing platform should be leveled, and there should be no uneven places.
2. The site of other composite air ducts such as double-sided aluminum foil insulation panel air ducts must be dry, the space should be large, and there must be space for stacking finished products. The processing site should reserve a transportation channel for on-site materials, finished products and semi-finished products.
3. The spiral duct machine should be cleaned regularly, and the hand-held direct air suction pipe can be used to clean up, and the brush is directly in contact with the inner wall of the pipeline to remove dirt. Using this method requires the duct to have large manholes for the operator to reach.